Amazon is about to start construction on the last part of its New Carlisle data center
Amazon's New Carlisle project is a $13.8 billion build
- $13.8 billion
- total cost of the project
- 32
- buildings planned, each about 216,000 square feet
- Over 1,000
- permanent employees hired so far
Source: InkFreeNews.com
The Amazon Web Services data center near New Carlisle is about halfway built. Half of the 32 planned buildings have been or are being built. Seven of nine on the northern campus are done and running AI models, an AWS vice president said. The other two should come online in the first half of 2027.
The South Bend Tribune reports nearly 18 buildings have gone up. The last campus, called SBN 210, could fill wetlands. At an Oct. 22 county meeting, an AWS representative said construction will eliminate 4.82 acres of wetland. The company plans to create 10.2 acres.
Amazon plans to create more than twice the wetland it will clear
Source: InkFreeNews.com
View as table
| Value | |
|---|---|
| Wetland cleared | 4.82 acres |
| Wetland to be created | 10.2 acres |
- South campus: eight of nine buildings expected operational in the coming weeks
- Last south building: targeted for early 2027
- SBN 210: no construction yet, and winter may stall it until spring
- Still to come: two to three more years of construction